On their own website PHD describe themselves as “The World’s ‘Go-To’ Scaffolding Specialists.”
The award of the contract to a scaffolding specialist will raise the eyebrows of some supporters who were promised state of the art retractable seating moved on wheels at the touch of a button.
Stadium owners E20 are trying to sue the administrators of Alto Seating for £1.4m while the administrators from the doomed company are trying to counter claim £1.5m from E20 for unpaid invoices.
LLDC CEO, David Goldstone gave evidence at the London Assembly Budget Monitoring sub-committee last year about the rising cost of the London Stadium operating costs and the impact of the failed retractable seating system which they now call relocatable seating.
Goldstone confirmed an extra £21m was spent on the doomed seating system last year and estimated costs could reach £8m per year to move the seats backwards and forward unless a better solution could be found.